Thursday, 21 March 2013
Friday, 15 March 2013
Wednesday, 13 March 2013
Day 3 Foundations dug out
Foundations all dug out. About 4m of the strip to the east wall of the living room had to be stepped down by 225 mm. Location of former tank has been filled with 4-6 inch stone under internal strips.
Steel mesh for reinforcing the foundations has arrived on site
Tuesday, 12 March 2013
Day 2: Foundations
Old tank excavated and will need to be filled. This was a bit bigger then we thought.
The ground is generally good though (stiff gravelly boulder clay) and dry
Monday, 11 March 2013